Construction Update: Three-Week Lookahead
Current Schedule: February 16, 2026 – March 8, 2026
Please be advised of the following active construction tasks in the East Quad area. Work is being carefully scheduled to minimize disruption to campus activities.
| Category | Task | Dates |
| Soil Excavation | Excavate top 2′ of soil from interior. | Feb 17 – Feb 20. |
| Soil Excavation | Dispose of soil. | Feb 17 – Feb 20. |
| Catch Basins | Survey and excavate CB-12 to CB-19. | Feb 21 – Feb 24. |
| Catch Basins | Install CB-12 to CB-19 and pipe. | Feb 25 – Feb 27. |
| Demo/Electric | Disconnect L1X fixtures and remove L2X/L3X fixtures. | Feb 23 – Feb 24. |
| Demo/Electric | Remove existing LX1 fixtures. | Feb 23 – Feb 24. |
| Mobilize | Install temporary fence at Phase 1 limits. | Mar 2. |
| Mobilize | Remove plywood fence at Phase 1 limits. | Mar 3 – Mar 4. |
| Demolition | Demo existing pathways. | Mar 6. |
Upcoming Phase 2 Closure
Please note that Phase 2 of the East Quad Renovation will officially run from March 1, 2026, to May 31, 2026.
- During this period, all areas highlighted within the Phase 2 boundary will be entirely closed to the public.
- This includes the eastern sections near the Library and the Ingersoll Entrance.
East Quad Phase 2 Closure Map – March to May 2026
Campus Impact & What to Expect
- Events: Outdoor events traditionally held on the East Quad will be relocated to the West Quad or inside the Student Center (SUBO).
- Tours: Campus tours will follow updated routes to avoid construction zones while still highlighting the best of our campus.
- Signage: New informational displays featuring project designs will be installed on the construction fencing in the coming weeks.
Questions?
For more information or specific inquiries regarding the construction schedule, please contact the Office of Finance and Administration at svpfa@brooklyn.cuny.edu