East Quad Renovation Project

Full Project Schedule Overview

Curious about the long-term timeline? You can view the chart for both the East Phase (March – May) and West Phase (June – August) below:
View the Full East & West Phase Project Schedule

There will be follow up after the West Phase that will limit access to the full East Quad. We will provide updates as they become available.

Construction Update: Two-Week Lookahead

Current Schedule: March 30, 2026 – April 12, 2026

Please be advised of the following active construction tasks in the East Quad area. Work is being carefully scheduled to minimize disruption to campus activities.

CategoryTaskDates
Catch BasinsExcavate and install Dewatering MH at IngersollApr 6
Catch BasinsExcavate and install Dewatering MH at BoylanApr 6 – Apr 7
Catch BasinsSurvey and Excavate CB-9 to 11, DMH-2Apr 6 – Apr 10
Catch BasinsSurvey and Excavate CB-25 to 29Apr 6 – Apr 10
Catch BasinsDOB Inspection for All Pipes SE corner and NE corner (except Boylan to MH-5, MH-2 to Relay)Apr 9
Catch BasinsBackfill all pipes inspected by DOBApr 9
Catch BasinsInstall Pipe from Boylan to MH-5Apr 13 – Apr 14
Catch BasinsDOB inspection Boylan to MH-5Apr 15
Catch BasinsBackfill all pipes inspected by DOBApr 15
Catch Basins12″ Relay into EX. MH-3Apr 9 – Apr 13
ConcreteElectrical Trench under Vehicular PathwayApr 15
ConcreteDemo Ramps and Concrete at StairApr 8 – Apr 13
ConcretePrep for Concrete CurbApr 16 – Apr 17
PlantingImport and stockpile Planting SoilApr 16 – Apr 17
ElectricalInterior Conduit Runs in IngersollApr 6 – Apr 10
ElectricalExterior Conduit Runs in East QuadApr 13 – Apr 17

Upcoming Phase 2 Closure

Please note that Phase 2 of the East Quad Renovation will officially run from March 1, 2026, to May 31, 2026.

  • During this period, all areas highlighted within the Phase 2 boundary will be entirely closed to the public.
  • This includes the eastern sections near the Library and the Ingersoll Entrance.

East Quad Phase 2 Closure Map – March to May 2026


Campus Impact & What to Expect

  • Events: Outdoor events traditionally held on the East Quad will be relocated to the West Quad or inside the Student Center (SUBO).
  • Tours: Campus tours will follow updated routes to avoid construction zones while still highlighting the best of our campus.
  • Signage: New informational displays featuring project designs will be installed on the construction fencing in the coming weeks.

Questions?

For more information or specific inquiries regarding the construction schedule, please contact the Office of Finance and Administration at svpfa@brooklyn.cuny.edu