Full Project Schedule Overview
Curious about the long-term timeline? You can view the chart for both the East Phase (March – May) and West Phase (June – August) below:
View the Full East & West Phase Project Schedule
Construction Update: Two-Week Lookahead
Current Schedule: March 30, 2026 – April 12, 2026
Please be advised of the following active construction tasks in the East Quad area. Work is being carefully scheduled to minimize disruption to campus activities.
| Category | Task | Dates |
| Catch Basins | Excavate and install Dewatering MH at Ingersoll | Apr 6 |
| Catch Basins | Excavate and install Dewatering MH at Boylan | Apr 6 – Apr 7 |
| Catch Basins | Survey and Excavate CB-9 to 11, DMH-2 | Apr 6 – Apr 10 |
| Catch Basins | Survey and Excavate CB-25 to 29 | Apr 6 – Apr 10 |
| Catch Basins | DOB Inspection for All Pipes SE corner and NE corner (except Boylan to MH-5, MH-2 to Relay) | Apr 9 |
| Catch Basins | Backfill all pipes inspected by DOB | Apr 9 |
| Catch Basins | Install Pipe from Boylan to MH-5 | Apr 13 – Apr 14 |
| Catch Basins | DOB inspection Boylan to MH-5 | Apr 15 |
| Catch Basins | Backfill all pipes inspected by DOB | Apr 15 |
| Catch Basins | 12″ Relay into EX. MH-3 | Apr 9 – Apr 13 |
| Concrete | Electrical Trench under Vehicular Pathway | Apr 15 |
| Concrete | Demo Ramps and Concrete at Stair | Apr 8 – Apr 13 |
| Concrete | Prep for Concrete Curb | Apr 16 – Apr 17 |
| Planting | Import and stockpile Planting Soil | Apr 16 – Apr 17 |
| Electrical | Interior Conduit Runs in Ingersoll | Apr 6 – Apr 10 |
| Electrical | Exterior Conduit Runs in East Quad | Apr 13 – Apr 17 |
Upcoming Phase 2 Closure
Please note that Phase 2 of the East Quad Renovation will officially run from March 1, 2026, to May 31, 2026.
- During this period, all areas highlighted within the Phase 2 boundary will be entirely closed to the public.
- This includes the eastern sections near the Library and the Ingersoll Entrance.
East Quad Phase 2 Closure Map – March to May 2026
Campus Impact & What to Expect
- Events: Outdoor events traditionally held on the East Quad will be relocated to the West Quad or inside the Student Center (SUBO).
- Tours: Campus tours will follow updated routes to avoid construction zones while still highlighting the best of our campus.
- Signage: New informational displays featuring project designs will be installed on the construction fencing in the coming weeks.
Questions?
For more information or specific inquiries regarding the construction schedule, please contact the Office of Finance and Administration at svpfa@brooklyn.cuny.edu