Construction Update: Three-Week Lookahead
Current Schedule: March 9, 2026 – March 22, 2026
Please be advised of the following active construction tasks in the East Quad area. Work is being carefully scheduled to minimize disruption to campus activities.
| Category | Task | Dates |
| Soil Excavation | Dispose Soil from WC-1 | Mar 9 |
| Soil Excavation | Dispose Soil from WC-6 and 9 | Mar 12 – Mar 13 |
| Demo/Electric | Remove existing fixtures | Mar 9 – Mar 10 |
| Catch Basins | Survey and Excavate CB-9 to 11, DMH-2, Dewatering MH | Mar 9 – Mar 11 |
| Catch Basins | Install Dewatering MH, CB-12 to CB-19, DMH-2 and DIP | Mar 11 – Mar 20 |
| Light Pole Foundation | OFFSITE: Fabricate Pre-cast Lightpole Foundations | Mar 9 – Mar 20 |
| Tree/Planting | OFFSITE: Tree Tagging | Mar 9 |
Upcoming Phase 2 Closure
Please note that Phase 2 of the East Quad Renovation will officially run from March 1, 2026, to May 31, 2026.
- During this period, all areas highlighted within the Phase 2 boundary will be entirely closed to the public.
- This includes the eastern sections near the Library and the Ingersoll Entrance.
East Quad Phase 2 Closure Map – March to May 2026
Campus Impact & What to Expect
- Events: Outdoor events traditionally held on the East Quad will be relocated to the West Quad or inside the Student Center (SUBO).
- Tours: Campus tours will follow updated routes to avoid construction zones while still highlighting the best of our campus.
- Signage: New informational displays featuring project designs will be installed on the construction fencing in the coming weeks.
Questions?
For more information or specific inquiries regarding the construction schedule, please contact the Office of Finance and Administration at svpfa@brooklyn.cuny.edu