• East Quad Walkway Closure

    Access to the East Quad pedestrian walkways will be closed from Friday, October 2 at 11:00 p.m. through Monday, October 5 at 6:00 a.m. while contractors apply concrete sealer to the new walkways. The notice provides alternate entrances for Boylan and Ingersoll Halls during this period.

  • Campus Advisory – Inclement Weather

    Due to inclement weather expected this weekend, the campus community is asked to close windows and doors in offices, labs, storage areas, and unoccupied spaces where possible to help prevent water infiltration and facility damage. Please report any leaks, flooding, or damage to Facilities at x5885 or through the Archibus work order system as soon as possible.

  • Rescheduled: Campus Wide Roof Gutters & Leaders Replacement Project

    The Campus-Wide Roof Gutters & Leaders Replacement project has been rescheduled to begin October 5. The project will include roof leak testing at Boylan, Roosevelt, Ingersoll, and Whitman Halls and may require temporary access to offices and rooms, as well as closed windows during testing.

  • Whitehead Campus Road Entrance – Deliveries

    The Whitehead Campus Road entrance is scheduled to reopen on September 8 for foot traffic only through September 26 while the new concrete cures. During this period, carts, dollies, hand trucks, and other heavy equipment are prohibited, with heavier deliveries directed through the Library Cafe entrance in coordination with Cafe staff.

  • Whitehead Campus Road Entrance – Deliveries

    The Whitehead Campus Road entrance is scheduled to reopen on September 8 for foot traffic only through September 26 while the new concrete cures. During this period, carts, dollies, hand trucks, and other heavy equipment are prohibited, with heavier deliveries directed through the Library Cafe entrance in coordination with Cafe staff.

  • Attention: East Quad – Bedford Entrance Opening

    The East Quad Bedford Entrance is scheduled to reopen on August 28, in time for the first day of classes. While the entrance and access to Boylan and Ingersoll Halls will be available, the interior of the Quad will remain closed as work continues.

  • Completed: Paving of Boylan Hall well parking lot

    The repair and repaving of the Boylan Hall well parking lot has been completed ahead of schedule. The parking lot will reopen tomorrow, Thursday, August 20th. Thank you for your cooperation.

  • Reminder: Campus-wide Tree Removal/Pruning

    The repair and repaving of the Boylan Hall well parking lot has been completed ahead of schedule. The parking lot will reopen tomorrow, Thursday, August 20th. Thank you for your cooperation.

  • Reminder: Paving of Boylan Hall well parking lot

    The Boylan Hall well parking lot will be closed for repair and paving from Tuesday, August 18, through Thursday, August 20. Please use alternate routes around campus and the main parking lot as needed. Signage will direct pedestrians and staff, and exit doors to the lot will be blocked for safety during the work.

  • Postponement: Campus Wide Roof gutters & Leaders Replacement Project

    The Campus-Wide Roof Gutters & Leaders Replacement project has been postponed to a later date to allow ongoing work in the East Quad and Boylan Well to be completed without interruption. The project will also require new permits before work can begin.